REPORT #20

PROGRESS REPORT #20

Let’s build back better.

8th August 2022.

_________________________________________________________________________

MAST BUILDING & SPAR REPAIRS

First primer coat on the new mizzen mast.

BOWSPRIT

STEM

Mike Howett explaining to Far Horizon Capt. Miguel and Engineer Ivan the details of the new stem construction.

NEW STERN POST PROGRESS.

Engineering and woodwork combined.

NEW GARBOARD PLANKS.

13 x 30mm bronze through bolts connect both Garboard planks plus bronze spokes into the American Oak false keel.

Full team, full time

TAKIAN THONG PLANKING IN KILN DRYER

Moisture content reduced to 10-12%.

STEERING & RUDDER REBUILD.

No such thing as a small job on the Cariad rebuild.

Rudder remedial work after the demage from Toredo Worm

Steering gear overhaul.

RE-CAULKING TEAK DECK.

INTERIOR WOODWORK

Getting access to planking bolts. This remedial work is a direct result from leaving the boat in the water for 12 years without dry docking.

Imagine coming to work each morning and being faced with this…

PAINT

Even through the grot the beauty is still there.

VARNISH

STEELWORK

File photos 2007.

Tabs for bronze thru-bolts completed. Ready for Garboard planks.

Des Kearns

Cariad Project Manager

8th August 2022.