REPORT #30

PHOTO PROGRESS REPORT #30.

INTERIOR

_________________________________________________________________________

Three teams fitting out…..

One team forward.

One team amidships.

One team master stateroom.

PLANKING

Starboard side ready for paint application.

3M 5200 being applied to caulked seams.

NEW GENERATOR PLATFORM

New generator platform

RUDDER

Fitted and copper sheathing applied to specific areas to stop Toredo worms.

Des Kearns

Cariad Project Manager

9th January 2022.