PROGRESS REPORT #28.

_________________________________________________________________________

Overview.

  • Hull planking is complete using temporary bolts. Waiting on Nickel Alu Bronze bolts from UK so we can complete hull planking.
  • Meanwhile completed sections are being caulked.
  • New shipment of Oakum from Davey UK is stuck in Customs.
  • Modified interior fit-out has commenced in accordance with Paul Spooner’s drawings and Tim’s requirements. Three carpentry teams working in three different areas.
  • Bulwarks painting complete and finished teak deck and deck has been covered with lino.
  • Juha team pushing ahead on new hollow spars.
  • New Kohler 20.5 Kva Genset in on site ready for installation.
  • First wire shipment and Watermaker already on site..

HOLLOW SPAR BUILDING.

INTERIOR

PLANKING COMPLETED USING TEMPORARY BOLTS. WAITING ON UK BOLTS.

TEAK DECK FINISHED AND PROTECTED.

Des Kearns

Cariad Project Manager

15TH December 2022.