REPORT #14

PROGRESS REPORT #14

14th June 2022.
_________________________________________________________

ENGINE ROOM & INTERNAL STEEL REDUCTION

A blank canvas.

We left the basic framework.

PAINT

Paint team powering ahead.

4 coats Jotamastic 87 before white topcoats.

“RABBIT” (REBATE) PLANK.

Prep for the Garboard Plank

The rabbit.

NEW STEM.

Bobstay fitting

New stem

STERN POST & ASSOCIATED STEELWORK.

Going…

Going…

Gone….this approach gives us long term solution and an opportunity to completely renew the stern section.

MAST BUILDING & SPAR REPAIRS

Our mast building shed showing new mizzen mast under construction.

Partially finished Douglas Fir mizzen mast.

GENSET

Rebuilt Northern Lights 12 Kva Genset.

GARDNER 8LXB ENGINE

Condition during installation in 2008.

After 3 submerging in sea water. Rebuild in progress.

WINCHES

Anchor winch overhaul

VARNISH

Des Kearns

Cariad Project Manager

14th June 2022